Temporary limitation production of power

Last updated on: 2024-07-02
Date and time of notification Asset name Maximum power

(MW)
Unavailability reason Unavailable Capacity

(MW)
Event type Status of the execution Market participant
2021-07-07 19:03:17 Pątnów 1 B2 222 niesprawne urzadzenia pomocnicze kotla 222 Unplanned Ended ZE PAK SA
2021-07-02 07:55:54 Pątnów 1 B1 222 nieszczelny uklad pierwotny 222 Unplanned Ended ZE PAK SA
2021-06-29 18:40:21 Pątnów 1 B1 222 Niesprawny kociol 222 Unplanned Ended ZE PAK SA
2021-06-26 01:16:19 Pątnów 1 B1 222 ograniczone dostawy wegla 222 Unplanned Ended ZE PAK SA
2021-06-21 18:58:23 Pątnów 1 B1 222 niesprawne urzadzenia pomocnicze turbiny 222 Unplanned Ended ZE PAK SA
2021-06-21 01:14:05 Pątnów 1 B2 222 remont sredni 222 Planned Ended ZE PAK SA
2021-06-19 01:34:17 Pątnów 1 B1 222 Niesprawny pomiar temp. pary na turbinie 222 Unplanned Ended ZE PAK SA
2021-06-16 08:22:10 Pątnów 1 B1 222 Remont sredni 222 Planned Ended ZE PAK SA