Temporary limitation production of power

Last updated on: 2024-06-25
Date and time of notification Asset name Maximum power

(MW)
Unavailability reason Unavailable Capacity

(MW)
Event type Status of the execution Market participant
2015-10-21 21:53:38 Pątnów 2 B9 474 stabilizacja kotła przed pomiarami 278 Unplanned Ended EP II sp. z o.o.
2015-10-19 12:46:18 Pątnów 1 B3 200 Nieszczelny podgrzewacz wody 200 Unplanned Ended ZE PAK SA
2015-10-18 14:52:51 Pątnów 1 B2 222 - 222 Planned Ended ZE PAK SA
2015-10-17 12:05:35 Pątnów 2 B9 474 awaria turbopompy 200 Unplanned Ended EP II sp. z o.o.
2015-10-17 07:34:24 Pątnów 1 B3 200 nieszczelnosc w kotle 200 Unplanned Ended ZE PAK SA
2015-10-16 09:52:04 Pątnów 1 B4 200 ograniczone odsiarczanie 200 Unplanned Ended ZE PAK SA
2015-10-15 11:06:56 Pątnów 1 B6 200 ograniczone odsiarczanie 200 Unplanned Ended ZE PAK SA
2015-10-14 06:58:33 Pątnów 1 B2 222 oswajanie inwestycji 222 Planned Ended ZE PAK SA