Temporary limitation production of power
Last updated on: 2024-11-23
Date and time of notification | Asset name | Maximum power (MW) |
Unavailability reason | Unavailable Capacity (MW) |
Event type | Status of the execution | Market participant | ||
---|---|---|---|---|---|---|---|---|---|
2016-03-14 06:50:35 | Pątnów 1 B2 | 222 | TG-niesprawny pomiar drgań łożyska nr7 | 222 | Unplanned | Ended | ZE PAK SA | ||
2016-03-13 00:19:19 | Pątnów 1 B2 | 222 | niesprawne dwie PWZ | 222 | Unplanned | Ended | ZE PAK SA | ||
2016-03-09 23:02:58 | Pątnów 1 B4 | 200 | brak możliwosci odsiarczania | 200 | Unplanned | Ended | ZE PAK SA | ||
2016-03-08 11:09:15 | Pątnów 1 B2 | 222 | Niesprawne dwie PWZ | 222 | Unplanned | Ended | ZE PAK SA | ||
2016-03-08 09:25:48 | Adamów B4 | 120 | Ograniczone dostawy węgla z KWB | 120 | Unplanned | Ended | ZE PAK SA | ||
2016-03-06 09:23:29 | Pątnów 1 B4 | 200 | Ograniczone odsiarczanie | 200 | Unplanned | Ended | ZE PAK SA | ||
2016-02-22 09:50:05 | Pątnów 1 B1 | 222 | zadziałanie zab. pary wtórnej | 222 | Unplanned | Ended | ZE PAK SA | ||
2016-02-08 11:55:37 | Pątnów 1 B1 | 222 | Remont bieżący | 222 | Unplanned | Ended | ZE PAK SA |