Temporary limitation production of power

Last updated on: 2024-11-22
Date and time of notification Asset name Maximum power

(MW)
Unavailability reason Unavailable Capacity

(MW)
Event type Status of the execution Market participant
2014-10-29 07:50:17 Pątnów 1 B3 200 Nieszczelny kocioł 200 Unplanned Ended ZE PAK SA
2014-10-28 22:40:54 Pątnów 2 B9 474 TG-9 nieszczelny rurociąg pary do uszczelnień 474 Unplanned Ended EP II sp. z o.o.
2014-10-27 08:06:56 Adamów B3 120 Spadek temperatury pary wtórnej 120 Unplanned Ended ZE PAK SA
2014-10-25 20:55:34 Pątnów 2 B9 474 - 200 Unplanned Ended EP II sp. z o.o.
2014-10-24 23:19:20 Pątnów 1 B3 200 K-3 nieszczelny podgrzewacz wody 200 Unplanned Ended ZE PAK SA
2014-10-24 09:27:23 Pątnów 1 B5 200 uszkodzony dopalacz żużla 200 Unplanned Ended ZE PAK SA
2014-10-24 05:12:59 Pątnów 2 B9 474 utrudnione odpopielanie 278 Unplanned Ended EP II sp. z o.o.
2014-10-20 17:29:27 Pątnów 2 B9 474 Remont średni 474 Planned Ended EP II sp. z o.o.