Temporary limitation production of power
Last updated on: 2024-11-22
Date and time of notification | Asset name | Maximum power (MW) |
Unavailability reason | Unavailable Capacity (MW) |
Event type | Status of the execution | Market participant | ||
---|---|---|---|---|---|---|---|---|---|
2014-09-26 07:38:25 | Pątnów 1 B5 | 200 | remont średni | 200 | Planned | Ended | ZE PAK SA | ||
2014-09-22 18:19:55 | Pątnów 1 B4 | 200 | BL.4 nieszczelny kocioł | 200 | Unplanned | Ended | ZE PAK SA | ||
2014-09-20 23:27:16 | Adamów B5 | 120 | Ograniczone dostawy węgla z KWB | 120 | Unplanned | Ended | ZE PAK SA | ||
2014-09-20 23:24:53 | Adamów B3 | 120 | Ograniczone dostawy węgla z KWB | 120 | Unplanned | Ended | ZE PAK SA | ||
2014-09-20 14:17:07 | Pątnów 2 B9 | 474 | utrudnione odpopielanie | 278 | Unplanned | Ended | EP II sp. z o.o. | ||
2014-09-19 23:17:34 | Pątnów 1 B6 | 200 | nieszczelny kocioł | 200 | Unplanned | Ended | ZE PAK SA | ||
2014-09-18 06:10:31 | Pątnów 2 B9 | 474 | utrudnione odpopielanie | 278 | Unplanned | Ended | EP II sp. z o.o. | ||
2014-09-13 07:45:04 | Pątnów 1 B4 | 200 | nieszczelność w kotle | 200 | Unplanned | Ended | ZE PAK SA |